Logo UCM buildingSMART International
  • Aucun résultat trouvé
  • Cas d'utilisation
  • Co-Creation Space
  • Communauté
    • buildingSMART
      • buildingSMART International
      • buildingSMART Autriche
      • buildingSMART Benelux
      • buildingSMART Allemagne
      • buildingSMART Switzerland
    • Organisations
      • HSLU
    • Partenaires de collaboration
      • Entreprises
      • Associations & Institutions
      • Expert
  • fr
    • en
    • de
    • fr
  • Connexion
Emplacement
buildingSMART Switzerland Andreasstrasse 5 8050 Zurich (Switzerland)ucm@buildingsmart.ch
Société
AccueilÀ proposCommunautéFormation
Ressources
Cas d'utilisationCo-creation spaceNotes de versionFAQ
buildingSMART Logo
Copyright © 2025 buildingSMART. Tous droits réservés.
ContactDéclaration de confidentialité et de cookiesTermes et conditions
Small IconAI Chat
    • Accueil
    • Cas d'utilisation
    • Clash Detection

    Clash Detection

    Cas d'utilisation Définition du Document

    Exigences d'échange

    Impression

    Groupe de Projet

    • Marcin Grzelak, m.grzelak@mostostal.waw.pl
    • Christopher Kowal, c.kowal@mostostal.waw.pl

    Droits d'auteur

    All dokuments are licensed as a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License
    (Attribution-Non-Commercial-ShareAlike 4.0). Further information can be found at

    creativecommons

    Manipulation

    The documents reflect the current best practice and do not claim to be complete. They should not to be understood in the sense of a generally valid recommendation or guideline from a legal point of view. The documents are intended to support appointing and appointed parties in the application of the BIM method. The documents must be adapted to the specific project requirements in each case. The examples listed do not claim to be complete. Its information is based on findings from practical experience and is accordingly to be understood as best practice and not universally applicable. Since we are in a phase in which definitions are only emerging, the publisher cannot guarantee the correctness of individual contents.

    Commentaires

    Chargement des commentaires...

    PAS ENCORE INSCRIT?


    Inscrivez-vous au Service de Gestion des Cas d'Utilisation gratuitement pour commencer à créer votre premier cas d'utilisation.


    Les utilisateurs inscrits peuvent utiliser la zone de téléchargement et les fonctions de commentaire.

    Clash Detection
    Type de Document
    Cas d'utilisation
    GUID
    3F62144A-BB77-4C8D-A4D3-6BB14296B938
    Identifiant
    BIMSpeed_UC15_MOW
    Phase du Cycle de Vie
    ISO 22263
    Révision
    -
    Statut du Projet
    Approuvé
    Niveau de Maturité
    Perspective
    Publié le
    31 août 2022
    Dernière Modification
    1 sept. 2022
    Éditeur
    BIM Speed
    Auteurs
    • Chris Kowal Kowal
    • Marcin Grzelak

    Résumé de la Gestion

    Clash detection is a procedure for detecting geometrical collisions between model elements of different disciplines and BIM models. It is an automated process where two or more models can be checked for these collisions using specified rules and tolerances. Clash detection is an integral component of the BIM process. It improves coordination between disciplines and has the overall effect of reducing costs and mistakes in a project.

    Objectif et Portée

    The proposed use case aims to perform clash detection analysis between BIM models in an automated, rule-based manner.

    Description

    This procedure is an important step in the BIM collaboration process. Having multiple designers working on different models leaves room for error, where different elements can clash, meaning at least part of one element collides with another at the same location or that certain tolerances are exceeded. These clashes can be checked automatically through tools using models and clash detection rules as input. These rules are created for determining what kind of object collisions will be understood to be clashes as well as any tolerances an element has. After the program automatically checks two or more models against each other for clashes, designers or coordinators have to go through them and confirm if they are indeed clashes and find a solution to fix them.

    Phases du Cycle de Vie

    ISO 22263

    Objectifs & Avantages du BIM

    Clash detection should have the overall effect of:

    • Saving time by quickly performing the task
    • Ensuring the compatibility between models and disciplines
    • Keeping a project on schedule by preventing avoidable delays in both the design and construction phase of a project by catching mistakes early on
    • Saving time in communicating clashes through issue management tools

    Délimitation

    Individual clashes detected by the program must be analyzed manually by the designer who must decide if each one is relevant. The clashes will need to be fixed by the responsible designers.

    Cas d'Utilisation Référencés

    Model Checks for compliance testing and design coordination

    Abréviations

    IFC: Industry Foundation Class

    Description

    Clash detection relies on openBIM format IFC files which are exported from authoring software. These IFC files are then uploaded into the Clash Detection software being used. These are then checked against other models using the software’s clash detection tool. After performing the clash detection, issues are created and shared to relevant project participants where they will help coordinate fixing model geometry. If the users are working within the same collaboration environment, they may not need to exchange any files, however if they are not, then BCF files including information on the clashes may be exchanged between users, which can then be read into authoring software.

    Images

    • pic12_exchange.png (png | 7,49 KB)

    Processus

    Diagramme de Processus

    Processus Global

    Description

    Preparing assumptions and rules for clash detection

    In this phase the following items should be discussed and documented:

    • The needs of the project and project participants regarding 3D coordination.
    • The definition of a clash and specifying which clashes are relevant or not.
    • A clash detection matrix should be prepared in order to specify which models and which disciplines are going to be checked against each other.
    • Based on the clash detection matrix, the rules and tolerances should be clearly stated. They should be checked and revised if needed to see if they fulfill project needs. The final assumption set will be used during the Clash Detection process. This set is input into the checking tool by the person performing the Clash Detection.

    This process is necessary to be able to program the rules into a clash detection software.

    Model quality check before clash detection

    Before performing clash detection all the models need to undergo quality checks in order to determine whether they meet minimum requirements for clash detection at a given stage. 

    The most common indicators of model quality are:

    • Adherence to federation strategy/model breakdown strategy
    • Consistent naming according to naming convention
    • Content of the model should be consistent with its discipline
    • Model should be properly situated in the global coordination system
    • All the elements in the model should have the minimum information needed for their categorization and identification
    • All the elements in the model should have a proper level of geometric detail for a given stage.
    • There should be no duplicates between different models.

    It is advised to use a standard model quality checklist before every clash detection session.

    Performing clash detection

    As soon as the models are checked and ready, the clash detection can start.

    • Firstly, all the models are loaded in order to create a federated model.
    • Then the programmed clash rules should be executed. Each clash should be analyzed separately. Only if the clash is relevant then it should be reported. Clashes can be seen with or without the context of other elements.
    • Each clash or group of clashes is then reported as an issue. All the communicated issues create an issue register.
    • Issues are then synchronized to a cloud platform and communicated to respective discipline designers.
    • Reports of the number of clashes and issues are regularly created to verify the progress of 3D coordination.

    Issue management and closing

    All the identified issues should be discussed and resolved by designers. The next iterations of updated models are undergoing clash detection multiple times in order to limit the number of clashes to a minimum. If the clash is resolved, then the respective issue should be closed.

    The central issue register on cloud platform helps to manage and document the whole process.

    Demonstration Site- Case Study

    The following demonstration case, part of the European Project BIM-SPEED, is a renovation project for an underground passage located in Warsaw, Poland near Rondo Jazdy Polskiej. The currently unused passage will be deeply renovated and become a point of first contact for homeless people. The design process produced multiple discipline models including an architectural, structural, various installations, and site plan models. It was vital to accurately check models against each other in order to reduce future delays when construction begins as well as keep the project on budget for the City of Warsaw.

    Preparing assumptions and rules for clash detection

    • A clash detection matrix was prepared in order to specify which models and which disciplines are going to be checked against each other.

    • Based on the clash detection matrix, the rules and tolerances were formulated. An excerpt of the rules table used is shown below.

    Model quality check before clash detection

    Before performing clash detection all the models used underwent quality checks.

    It is advised to use a standard model quality check list before every clash detection session.

    Performing clash detection

    Firstly, all the models were loaded in order to create a federated model. The software used was BIMCollab ZOOM. Models were uploaded to the shared project by their respective users. They were also responsible for updating the models, as required.

    Then the programmed clash rules were executed:

    Each clash was analyzed separately. Only if the clash was relevant, was it reported:

     

    Each clash or group of clashes is then reported as an issue:

     

    All the communicated issues formed part of an issue register:

    Issues are then synchronized to a cloud platform and communicated to respective discipline designers using BCF file formats.

    Reports of the number of clashes and issues are being regularly created to verify the progress of 3D coordination:

    Issue management and closing

    All the identified issues were discussed and resolved by relevant designers. The entire process was iterative, with each subsequent updated model being checked against the rest each time. When the clash was resolved, then the respective issue was closed and archived.

    Results:

    During several iterations of clash detection, a total of 148 issues were identified and communicated to the lead designers.

    Images
    • pic1_processmap.jpg (jpg | 268,85 KB)
    • pic10_clash.png (png | 145,14 KB)
    • pic11_results.png (png | 398,92 KB)
    • pic1a_processmap.jpg (jpg | 100,86 KB)
    • pic1b_processmap.jpg (jpg | 124,71 KB)
    • pic1c_processmap.jpg (jpg | 132,54 KB)
    • pic2_matrix.PNG (PNG | 8,91 KB)
    • pic2_table.png (png | 18,31 KB)
    • pic3_modelcheck.png (png | 816,88 KB)
    • pic4_clash.png (png | 211,28 KB)
    • pic5_clash.png (png | 86,36 KB)
    • pic6_clash.png (png | 237,84 KB)
    • pic7_clash.png (png | 180,91 KB)
    • pic8_clash.png (png | 10,30 KB)
    • pic9_clash.png (png | 250,23 KB)

    ISO 22263

    1 | Conception of need

    It should be decided during this stage if clash detection between models will be a requirement later on in the design phase. If there are multiple models, especially when created by designers of different disciplines, it is highly recommended to perform clash detection. Procedures for how often and who is responsible for clash detection should also be outlined, for example in a BIM Execution Plan. 

    6 | Coordinated design (and procurement)

    This is the stage when clash detection actually occurs, as outlined in the above procedure. It is an integral part of the coordination process in a project that makes use of BIM models.